Liquidating damages calculation for hud construction

The developer was to subdivide the land and had authority to do so from the Council on certain conditions.One condition required improvements to a road before any subdivision and sale occurring.It wasn’t until after that time that the developer engaged Spiers to do the road works.The initial contract contained a liquidated damages clause.The developer initially contracted with Spiers to do construction work, but not to complete the road improvements.Practical completion was subsequently delayed by two months.

liquidating damages calculation for hud construction-16liquidating damages calculation for hud construction-1

Spiers argued this was a penalty and therefore unenforceable.

For the clause to be enforceable, the damages specified must represent a genuine pre-estimate of loss that the aggrieved party is likely to suffer as a result of the other party’s breach.

This amount is calculated at the time of entering into the contract.

So, a court will enforce the provision, as each party is expected to hold up their end of the bargain.

However, there are limits on the enforceability of liquidated damages clauses.

Leave a Reply